This manual explains how to set up and activate the Ditio–Novorender integration, enabling access to machine locations and geolocated checklists in Novorender's 3D viewer.


Minimum Requirements

  • A project in Ditio

  • Access credentials for Ditio and Novorender

  • Assigned coordinate system for the project in Novorender

  • Admin permissions in both platforms


Step 1: Set Up Integration in Ditio

  1. Log in to Ditio's integration panel Ditio Integration Page

  2. Click the blue button labeled “Add Client”.
    ​

  3. In the popup form titled Add Client, fill in the following:

    • Client name: Novorender

    • Valid until: Select a future date (e.g., a year from now)

    • User to emulate: Select the relevant user (if applicable)

    • Allowed scopes: Enable all options:

      • Ditio core

      • Ditio mass transport

      • Ditio Legacy (or other available options)

  4. Click Add Client to save.
    ​


Step 2: Retrieve API Credentials

  1. Once the client is added, find the client row (e.g., Novorender) in the integration list.

  2. Click the three-dot menu (⋮) on the right side of the row.

  3. Select Update from the dropdown.
    ​

  4. A new form will open showing:

    • Client ID

    • Client Secret

  5. Copy both values securely. You will need them for the Novorender platform.
    ​


Step 3: Configure Novorender

  1. Open Novorender Explorer.

  2. Go to:

    • Advanced Settings > Features > Widgets

    • Enable the toggle for Ditio

    • Click Save

  3. Navigate to:

    • Integrations > Ditio

  4. Paste the Client ID and Client Secret into the respective fields.

  5. Click Save.
    ​


Outcome

Once setup is complete:

  • Swap the view to 2D mode to see the markers.

  • Novorender will pull machine positions from Ditio. Note! It is crucial to choose the coordinate system for the project in Novorender in order for this feature to work.

  • Checklists will appear geolocated directly within the 3D viewer interface.

  • Project stakeholders can now visualize real-world field data overlaid on project geometry.
    ​